Memo

 

To: Albert Schwarzkopf

From: Team 3

Subject: Progress for the Week ending 11-24-08

Date: 11-23-08

 

Significant Team Accomplishments

This week, we were able to correct many of the issues that we were having. Many of the queries that were giving us trouble have been corrected. We have also added the additional MAE pages to the new website. Also, we are now able to populate the text boxes on the forms with the correct information for each record.

 

Problems Addressed this Week

This week, the only problem we had was with time conflicts. Kristen and Kayla were unable to attend a working meeting at Tinker and Kristen was unable to attend a Sunday night working meeting due to another group project meeting.

 

Plans for Next Week

Next week, our team’s is to have the entire project completed. We are scheduled to give our final presentation on December 5, 2008 at 2:00 PM. We will prepare the presentation slides and make last minute touch-ups to the Final Report and the documentation.

 

Team Member

Activities

Hours

This

Week

Total Project Hours

Joann Brown

Attended group meetings and working meeting with the client. Worked towards correcting the query errors.

13.0

5.0

Jonathan Smith

Attended group meetings and working meeting with the client. Worked towards correcting the query errors.

13.0

5.0

Kayla Medina

Attended group meetings. Worked towards correcting the query errors. Created new web pages and worked on documentation.

8.5

5.0

Kristen Johnson

Attended group meetings. Created and turned in weekly report. Worked towards correcting the query errors.

8.5

5.0

TOTALS

 

43.0

20.0