Memo

 

To: Albert Schwarzkopf

From: Kristen Johnson for Team 3

Subject: Progress for the Week ending 10-13-08

Date: 10-12-08

 

Significant Team Accomplishments

This week, our group took a small break. We had two members of the team out of town from Thursday until late Sunday night. We met for a short time Wednesday night to download the VMWare program. We have begun to look at the code from Tinker and are making progress towards the end result.

 

Problems Addressed this Week

We were not faced with any major problems this week. Two members of the team were out of town for the weekend at our annual OU/TX game so we did not meet on Sunday like we normally do.

 

Plans for Next Week

Next week, our team will begin to start creating the web interface and try to restructure the code to work with SQL Server. We are meeting with the client on Friday for the first progress meeting. 

 

Team Member

Activities

Hours

This

Week

Total Project Hours

Joann Brown

Attended group meeting.

1.0

0.0

Jonathan Smith

Attended group meeting. Set up everyone with VMWare. 

2.0

0.0

Kayla Medina

Attended group meeting.  

1.0

0.0

Kristen Johnson

Attended group meeting. Created and turned in weekly report. 

2.0

0.0

TOTALS

 

6.0