Significant
Team Accomplishments
This week, the team met for the first time. We established the roles and tasks that each individual will be responsible for and began creating the Team Organization Plan. Completed the team contract and skills inventory summary. We also assigned the remaining components of Deliverable 1 to individual team members. The team discussed each member’s individual schedules and possible weekly meeting times.
Problems
Addressed this Week
Our team was presented with two minor setbacks this week. We gained a new member and spent some time to catch them up to speed. It will also be a challenge to coordinate all of our individual schedules to arrange meeting times.
Plans for
Next Week
Next week, our team will complete and turn in the Team Organization Plan. We also expect to create the first version of the SOW and edit the SOW.
Team Member |
Activities |
Hours This Week |
Total Project Hours |
Joann Brown |
Attended group
meeting. Accepted role as Standards Manager.
Contributed to the Team Organization Plan. |
2.0 |
3.0 |
Jonathan Smith |
Attended group meeting. Accepted role as
Coordinator. Contributed to the Team
Organization Plan and created a Gantt chart for the Project Schedule. |
3.5 |
5.5 |
Kayla Medina |
Attended group
meeting. Recorded and contributed to the first draft of the Team Organization
Plan. |
2.0 |
3.0 |
Kristen Johnson |
Attended group meeting and recorded progress.
Accepted role as Communicator. Created skills inventory and weekly report.
Contributed to the first draft of the Team Organization Plan. Edited and revised Team Organization Plan. |
4.5 |
5.5 |
TOTALS |
|
13.0 |
17.0 |